Road maintenance 1

  • Snow removal & sand application

Harvest 4

  • Limbing
  • Slashing
  • Felling
  • Skidding

Log trucking 2

  • Long-lenght log

    Transport path
    105 - mki témis - cameronian - ward - coulton

  • Shortwood

    Transport path
    105 - mki témis - cameronian - ward - coulton