REDPINE_COM
Activities may be cancelled or added during the current week.
Semaine du
7th Aug 23 au 13th Aug 23
Semaine du
14th Aug 23 au 20th Aug 23
Activity responsable:
Work prior to harvest 5
-
Road building
-
Tree clearing
-
Road shaping
-
Gravel
-
Road repair
Harvest 2
-
Logging & skidding
-
Limbing
Semaine du
21st Aug 23 au 27th Aug 23
Activity responsable:
Work prior to harvest 3
-
Tree clearing
-
Road shaping
-
Road repair
Harvest 3
-
Limbing
-
Felling
-
Skidding
Log trucking 1
-
Long-lenght log
Transport path
rte 20, rte 117, rte 105
Chantier’s name legend |
|
---|---|
Chantier’s name_COM | Chantier with commercial activities |
Chantier’s name_NCOM | Chantier with non-commercial activities |
Chantier’s name_invmar | chantiers d’inventaire et martelage |
Chantier’s name_CHE | chantiers de travaux d’implantation, de réfection ou d’amélioration de chemin situés à l’extérieur des chantiers commerciaux |